Client :
Tasman District Council.
Engineer :
MWH.
Contract Manager :
Mark Barr.
Completed Value :
$ 897,105.68.
Start Date :
April 2009.
Practical Completion Date :
October 2009.
Overview :
Roading and associated infrastructure upgrade of the Salisbury Rd / Talbot Street intersection in Richmond including installation of new traffic signals.
Specific Scope :
- Stormwater pipeline relay - 100Ø to 450Ø and associated manholes and sumps.
- Watermain relay - 63Ø to 150Ø and service laterals. Pressure testing and connection to TDC reticulation.
- Installation of new traffic signals.
- Saw cutting and cut to waste of existing pavement and kerb lines.
- Kerb & channel and footpath construction including laying of pavers and tactile pavers.
- New road pavement construction and surfacing.
- Landscaping and street furniture.
- Road marking and signage.
- Temporary traffic management on busy Richmond road located in multiple school zone.